Every alarm should require an action: do not leave "Expected operator action" empty. Set priority, delay and delivery channel per alarm. The ISA-18.2 / IEC 62682 approach is a common reference for alarm management. This template is not a compliance statement, so check the current text of the relevant standard. Italic rows are EXAMPLES only.
| No | Alarm tag | Alarm text | Source tag | Condition / limit | Delay | Priority (Urgent / Warning / Info) | Delivery | Expected operator action | Ack (Y/N) | Owner | Note |
| EXAMPLE 1 | | Well very high level | LT-101 | project-specific | project-specific | Urgent | SMS + e-mail | Go to site, check pump and level | | | |
| EXAMPLE 2 | | Pump fault | P-201 | project-specific | project-specific | Warning | SMS | Confirm the standby pump, call maintenance | | | |
| EXAMPLE 3 | | Communication lost | | project-specific | project-specific | Warning | E-mail | Check router, antenna and power | | | Heartbeat / connection supervision |
| EXAMPLE 4 | | Probe calibration date exceeded | | project-specific | project-specific | Info | Report | Add to maintenance plan | | | |
| EXAMPLE 5 | | Measurement error (wire break) | | project-specific | project-specific | Warning | SMS | Check sensor and cable | | | |
| 1 | | | | | | | | | | | |
| 2 | | | | | | | | | | | |
| 3 | | | | | | | | | | | |
| 4 | | | | | | | | | | | |
| 5 | | | | | | | | | | | |
| 6 | | | | | | | | | | | |
| 7 | | | | | | | | | | | |
| 8 | | | | | | | | | | | |