FAT Form (Factory Acceptance Test)

Mark the result columns: P = Passed, F = Failed, N = Not applicable. Scope, method and acceptance criteria follow the contract and technical specification (project-specific). This template is a general starting point, not a compliance or standards document.

0. General information

Project nameDocument no. / revision
Panel / systemFAT date / location
Manufacturer participantsCustomer participants

1. Documents before the test

NoCheck itemPFNNote
1.1Current electrical drawings and panel layout drawing
1.2I/O list (address, tag, description, signal type, engineering unit)
1.3Control logic description or functional design document
1.4Communication map (devices, protocols, addressing plan)
1.5Alarm list and priority definitions
1.6FAT form with test procedure and signature fields
1.7Version records of PLC and HMI/SCADA software
1.8Does the tested drawing match the built panel? (If not, the test is invalid.)

2. Visual and mechanical inspection (before power-up)

NoCheck itemPFNNote
2.1Labels match the drawing
2.2Panel size, door, hinge, lock, paint and protection class meet the specification
2.3Terminal tightness, cable supports, cable duct layout
2.4Earthing and protective conductor connections
2.5Separation of power and signal cables
2.6Fuse and breaker ratings match the drawing
2.7Spare terminals and free space for future additions
2.8Insulation and continuity measurements (project-specific)

3. I/O test

NoSignal type and test methodPFNNote
3.1Digital input: apply the signal by switch or jumper. Do the PLC address and SCADA tag change correctly?
3.2Digital output: give the command from PLC/SCADA. Does the correct relay or contactor pull in?
3.3Analog input: apply low, mid and high values. Are scaling, units and wire break detection correct?
3.4Analog output: write specific values. Does the measured output match the expected value?
3.5Emergency stop and safety: activate. Does the system reach the safe state?
3.6Signals tested: ______   Passed: ______   (If the field device is not available, use simulation or an injection device.)

4. Communication test

NoCheck itemPFNNote
4.1All devices visible and matching the addressing plan
4.2Data exchange with PLC, HMI, drive and meter is correct
4.3Communication fault alarm appears when a cable is pulled or a device is powered off
4.4System recovers when the connection returns
4.5Redundant changeover, if applicable (time and acceptance criterion project-specific)

5. Alarm and event test

NoCheck itemPFNNote
5.1Each alarm triggers once, with correct text, priority and timestamp
5.2Acknowledge and clear functions work
5.3No unnecessary or constantly repeating alarms
5.4Alarm and event records stored and retrievable
5.5Unauthorized users cannot perform restricted operations

6. Scenario (functional) tests

Write the start condition, steps and expected result for each scenario in advance.

NoScenarioPFNNote
6.1Normal start and stop sequence
6.2Auto/manual mode transitions
6.3Device failure and fallback to an intermediate stage
6.4Power loss and restoration
6.5Operator entering a wrong command
6.6System-specific functions (recipes, shifts, reporting etc.)
6.7.....................................

7. Records

NoCheck itemPFNNote
7.1Signed and dated FAT form
7.2Each test result marked (passed, failed, not applicable)
7.3Software versions and backups used are recorded
7.4Photos and screenshots taken, as needed
7.5Participant list (manufacturer and customer)
7.6Every change noted, affected tests repeated

8. Open items list (punch list)

NoDescription and test where foundSeverity (blocks shipment / can be closed on site)Owner and target dateClosure evidence and approver
1
2
3
4
5

9. Sign-off

NameSignatureDate
Manufacturer
Customer

This template is for general information. Acceptance criteria for your project should be set by the specification in your contract.