In a small plant, a SCADA project often starts with “let’s build the screen and be done.” Three years later the network is a mess, nobody has the tag list, and the server is a PC under a maintenance engineer’s desk. In this post we outline the skeleton of an architecture, at a scale of 1-5 PLCs and about 5000 tags, that does not cause pain later if set up correctly from the start. Most of the numbers change “depending on the project”; instead of making them up, we explain how to decide.
Layers: who talks to whom?
Even at a small scale, thinking about the layers separately makes the job easier:
- Field layer: sensors, drives, remote I/O, meters.
- Control layer: PLCs. Process logic runs here; even if SCADA stops, the machine should keep running.
- Supervisory layer: the SCADA server. It collects data from the PLCs and keeps alarms, trends and the event log.
- Presentation layer: operator clients, web/mobile views, reports.
- Upper layer (optional): data transfer to MES/ERP, the cloud or other systems.
The basic rule: control decisions in the PLC, visualization and logging in SCADA. Do not leave a critical interlock to a SCADA script.
Server / client layout
At this scale a single SCADA server and a few clients are often enough. When deciding, consider:
- How many operators will watch screens at the same time, and from where will they connect?
- Will data logging (historian) be on the same machine or in a separate database?
- Is remote access needed? If so, it should go through a controlled gateway, not directly to the server.
Running both the server and the operator screen on a single machine is common in small plants and is not wrong. However, if you do not want data collection to stop when the operator station fails, separate the server from the client.
Protocol choice: Modbus TCP, OPC UA, S7
| Protocol | Strength | Point to watch | Typical use |
|---|---|---|---|
| Modbus TCP | Simple, available on almost every device | Carries no data type or structure information, has no security features in its classic form; the address map is managed by hand | Meters, drives, third-party devices |
| OPC UA | Structured data, named tags, security and certificate support | May need to be enabled on the PLC model and license; load and session count depend on the project | Multi-brand environments, new projects |
| S7 (Siemens) | Direct, fast access to Siemens PLCs | Brand-dependent; access permissions must be configured on the PLC side | Sites made up only of Siemens |
Practical approach: if the PLC offers an OPC UA server and you need it, prefer it first; it is easier in terms of driver quality and security. For older devices or devices that do not support OPC UA, Modbus TCP or the brand’s own protocol comes into play. Mixing several protocols within the same SCADA is normal, as long as it is documented which device is connected with which protocol.
The default ports are known (502 for Modbus TCP, usually 4840 for OPC UA, 102 for S7); use them when writing firewall rules, but always verify the actual port from the device and software settings.
Tag counting: where does the 5000 figure come from?
The phrase “5000 tags” matters for licensing and performance, but not everyone counts the same thing. First settle the counting rule:
- Does the license count external tags connected to SCADA, or internal/calculated tags as well? This varies by vendor and package.
- Are an analog measurement’s value, alarm limits, status bits and command bits counted as separate tags?
- Is a structure (UDT/struct) counted as one tag, or as many tags as it has members?
Checklist:
- I extracted the I/O list and data blocks from all PLCs.
- For each I/O, I counted separately the values that need to appear in SCADA (measurement, status, alarm, command).
- I learned the license provider’s tag counting rule in writing.
- I separated the tags that will only be displayed from those that will be logged (trend/historian).
- I left room for machines or lines to be added in the near term (amount depends on the project).
- I added calculated and internal tags to the list separately.
As much as the tag count, scan time and logging rate also matter. You do not need to read all five thousand tags at the fastest period; putting slowly changing quantities into slow groups eases the load on both the network and the server.
Redundancy: what will you back up, and how much?
Doubling everything is not possible on small budgets; first consider the cost of downtime:
- Backup first, redundancy second. Regular, tested restore is essential for project files, PLC programs and the database. Most outages are prolonged not by hardware but by a configuration that cannot be restored.
- Server redundancy (hot/warm standby) is decided by the effect of an outage on the plant’s production or on legal records; its cost and complexity depend on the project.
- The PLC side must work independently. If SCADA is lost, the process should stay safe and controlled; if data can be buffered in the PLC, that is a plus.
- For network redundancy, a second path can be considered on critical lines; it is not needed for every cable.
- An uninterruptible power supply (UPS) and controlled shutdown often reduce more risk at lower cost than doubling the server.
Network segmentation
Even in a small plant, do not keep the office network and the automation network on the same flat network:
- Control network: PLCs, remote I/O, drives. A separate VLAN or physical switch if possible.
- Supervisory network: the SCADA server and operator stations.
- Office/IT network: ERP, email, general internet access.
- Demilitarized zone (DMZ): remote access and data transfer to external systems go through here, with controlled rules.
In this structure, firewall rules are the answer to “who, to whom, with which protocol”; the rule list should also be documented. Exposing PLCs directly to the internet, address conflicts and broadcast traffic problems are largely prevented by this separation. Make the IP plan up front; changing it later means visiting every PLC one by one.
Checklist before installation
- Layers and responsibilities (PLC logic / SCADA logging) are written down.
- A protocol-to-device mapping table has been prepared.
- Tag counting was done in line with the license rule.
- The backup and restore scenario has been tested.
- Network segments, IP plan and firewall rules are documented.
- The remote access path and authorization are defined.
- The alarm philosophy and user permissions are clarified.
Conclusion
In a plant with 1-5 PLCs, the success of SCADA depends largely on these architectural decisions made before screen design. Every decision is shaped by the plant’s production criticality, its existing device fleet and the budget; that is why the details are often set “depending on the project.”