Testing SCADA Screens Without a PLC

Trying a SCADA screen with simulated values before the PLC and panel are ready: what to test, which scenarios you need, and what simulation does not prove.

Published: · Author: Mekatrio team

In most projects SCADA screens start to be drawn before the panel and the PLC program are finished. If you try the screen only on site, when the real signals arrive, mistakes show up in the most expensive place: a wrong alarm threshold, overflowing text, a value with the wrong unit, a button that goes nowhere. This article explains how to try the screen with simulated values without a PLC, and what that trial does and does not prove.

The article describes a general method; which tool you use (a simulation driver, a PLC simulator or a test signal generator) differs from project to project. The values below are made up for explanation.

1. Why try the screen with simulation first?

  • Design mistakes are caught cheaply, and the trial time on site gets shorter.
  • You can review the screens with the operator before the panel arrives.
  • Alarm thresholds, colors and navigation order are tried with values produced on demand, not by “waiting for real data”.
  • You get a safe environment for training and demos.

2. Which values should you produce?

A single constant value does not reveal most mistakes. For each tag you want to be able to produce these behaviors:

Behavior What it is for
Constant value First opening of the screen, unit and decimal display
Slowly rising (ramp) Threshold crossings, color change, trend line
Oscillating (sine-like) Trend and gauge movement, an alarm coming and going
Small random movement Seeing real measurement noise and flicker on screen
Bit change Status lamps, running/fault display
Degraded value quality Trying the bad-quality display and the command lock
Communication loss What the screen shows when there is no data

A screen looks good in a simulation where values stay in the “normal” range. The real test of a screen is at the extremes.

3. A test scenario per screen

Write a short scenario list for each screen. Example (a made-up pump station screen):

Test How to simulate What you should see
Level thresholds Ramp the level beyond the upper and lower thresholds The right color and alarm at each threshold; consistent threshold order
Unit and decimals Give constant values Correct unit, readable decimals
Pump state Change the Running and Fault bits Status lamp and text correct; fault priority distinguishable
Bad quality Degrade the quality of a measurement The value is marked as invalid, the command button becomes inactive
Communication loss Cut the connection The screen does not show the old value as if it were current
Long text Enter a long label and description Text does not overflow or overlap
Navigation Go to all screens from the menu No button is left dangling; there is a way back
Trend Oscillate the values for a while Does the axis range clip the values; is the line readable

4. Consistency of alarm thresholds

Simulation is very good at exposing inconsistencies in alarm definitions. A mistake such as writing the “very high” threshold lower than the “high” threshold for a level shows up immediately when you drive the values beyond the thresholds. While writing alarm definitions, also run through the logic in the Alarm Management Guide: every alarm needs an action and a priority.

5. What does simulation not prove?

This section matters: even if the screen “works” in simulation, the following are not proven.

  • PLC logic. Pump rotation, interlocks and sequencing are tested with the real program, not with simulated values.
  • Communication. Address, data type, byte order, timing and line problems appear only with a real device.
  • Scaling and sensor behavior. The noise, delay and broken-wire behavior of a real sensor are not in the simulation.
  • Performance under real load. Whether the screen slows down has to be tried with the real tag load.

So simulation does not replace FAT and site commissioning; it is a preliminary step before them that clears screen-related mistakes. For the general frame see the FAT checklist note.

6. Keep simulation separate from production

  • Define the simulation source (connection) separately from the real PLC connection, and make its name show that it is a simulation.
  • Do not leave test switches (such as fault simulation) on the production screen, or protect them with authority. A “simulate fault” button on an operator screen is dangerous.
  • When sharing a screenshot, state that the image is a simulation. Do not present it as an image of a real plant.
  • When you switch the connection to the real PLC before commissioning, verify one by one that the tags really go to the real addresses.

7. Order of work

  1. Produce the tag list and the alarm definitions.
  2. Draw the screens; write the scenario list for each screen.
  3. Run the scenarios with simulation, record the mistakes and fix them.
  4. Review the screens with the operator or the operations lead.
  5. When the PLC and panel are ready, verify end to end in the FAT.
  6. On site, compare the signals with the screen one by one.

8. Checklist

  • Can behaviors such as constant, ramp and bit change be produced for each tag?
  • Was crossing each alarm threshold in both directions tried?
  • Were bad quality and communication loss tried on the screen?
  • Do long texts and units show on the screen without overflowing?
  • Do all navigation buttons work?
  • Is the simulation source separate from the real connection and clearly marked?
  • Were test switches removed from the production screen or protected with authority?
  • Are the things simulation does not prove in the FAT list?

Conclusion

Screen testing with simulation cheaply clears screen-related mistakes before the site, but it does not prove PLC logic, communication or real sensor behavior. Used in the right place it shortens the FAT; used with the wrong expectation it misleads. If you would like to plan together how the screens of your project will be tried off site, take a look at our SCADA installation service.