FAT checklist: panel and SCADA acceptance test

A practical checklist for panel and SCADA factory acceptance testing (FAT): documents, visual checks, I/O, communication, alarms, scenarios, open items.

Published: · Author: Mekatrio team

Why do we do FAT?

FAT (Factory Acceptance Test) is testing the panel and SCADA system in the manufacturer’s environment before it goes to site. The goal is this: to find faults before crane, transport and production-stoppage costs are incurred. A fault found on site is both expensive and puts pressure on everyone. The same fault found in the factory is just a work order.

The scope of the FAT, the test method and the acceptance criteria vary according to the contract or technical specification; all of it is set “depending on the project.” The list below is a general skeleton; use it by combining it with your own specification.

For a ready starting point where you can mark the results, open the FAT form; it is laid out for A4 and can be saved as PDF by printing from your browser.

1. Before the test: documents

Before starting the test, the following should be on the table:

  • Current electrical drawings and panel layout drawing
  • I/O list (address, tag, description, signal type, engineering unit)
  • Control logic description or functional design document
  • Communication map (devices, protocols, addressing plan)
  • Alarm list and priority definitions
  • FAT form with the test procedure and signature fields
  • Version records of the PLC and HMI/SCADA software

Whether the document is “current” is an important question. If the drawing being tested differs from the panel that was built, the test is wasted.

2. Visual and mechanical inspection

Before applying power, inspect the panel with open eyes:

  • Labeling: do terminal, cable and device labels match the drawing?
  • Do panel size, door, hinge, lock, paint and protection class comply with the specification?
  • Terminal tightness, cable supports, cable duct layout
  • Grounding and protective conductor connections
  • Separation of power and signal cables
  • Comparison of fuse and breaker ratings with the drawing
  • Spare terminals and free space inside the panel (for future additions)

The values and method of insulation and continuity measurements to be done before applying power are determined according to the project.

3. I/O test

Every signal must be verified end to end. If the field device is not available, use simulation or an injection device.

Signal type How it is tested What to check
Digital input Signal is applied with a switch or a jumper Do the PLC address and the SCADA tag change correctly?
Digital output Command is given from the PLC or SCADA Does the correct relay/contactor pull in?
Analog input Low, mid and high values are applied with a signal source Are scaling and units correct, is wire break detected?
Analog output Specific values are written by command Does the output measurement match the expected value?
Emergency stop and safety Activated Does it go to the expected safe state?

The result of each row is recorded on the form. “Most of it works” is not acceptance; the number must be clear: how many signals were tested, how many passed.

4. Communication test

  • Are all devices visible on the network, and do they match the addressing plan?
  • Is data exchange with devices such as the PLC, HMI, drive and meter correct?
  • When a cable is pulled or a device is switched off, does a communication fault alarm appear?
  • When the connection returns, does the system recover?
  • If there is a redundant structure, the changeover is checked; the duration and acceptance criteria are determined according to the project.

5. Alarm and event test

The value of SCADA lies in giving the right warning at the right time.

  • Each alarm is triggered once; text, priority and timestamp are checked
  • Acknowledging and clearing the alarm are tested
  • Is there any unnecessary or constantly repeating alarm?
  • Are alarm and event records stored, and can they be queried retrospectively?
  • Can an unauthorized user perform an operation they are not permitted to?

6. Scenario (functional) tests

Even if the I/O is correct one by one, the system can behave wrongly as a whole. Write scenarios that reflect real operation:

  • Normal start and stop sequence
  • Auto/manual mode transitions
  • Device failure and falling back to an intermediate stage
  • Power loss and restoration
  • Operator giving a wrong command
  • System-specific functions such as recipe, shift or reporting

For each scenario, the initial condition, steps and expected result must be written in advance.

7. Recording the results

When the test is finished, the records you should have are:

  • Signed and dated FAT form
  • The result of each test: passed, failed, not applicable
  • Software versions and backups used during the test
  • Photographs and, if necessary, screenshots
  • List of participants (manufacturer and customer side)

Every change made during the test must be noted. After a change, the affected tests are repeated.

8. Open items list (punch list)

The FAT is not expected to end clean; what matters is that the open items are listed. For each entry:

  • Description and in which test it was found
  • Severity (does it block shipment, can it be closed on site)
  • Responsible person and target date
  • Closure evidence and who approved it

Which items must be closed before shipment and which can be closed on site should be agreed at the start.

Quick checklist

  • Current documents are ready and their versions are noted
  • Visual and mechanical inspection is complete
  • All I/O signals were tested end to end
  • Communication and fault behavior were verified
  • Alarms, acknowledgments and permissions were tested
  • Scenario tests were done
  • Results were recorded with signatures
  • Open items were listed, with a responsible person and date assigned
  • Software backups were taken

Conclusion

A good FAT reduces the number of surprises on site. Writing the test plan at the order stage, clarifying the specification and determining the participants in advance make the job easier. If you need installation and commissioning support for your panel and SCADA to move to site smoothly, you can look at our site installation and commissioning service.