Water and wastewater facilities are spread out: the wells, pumping stations, tanks and treatment plant can be kilometers apart. Where the operator cannot visit every point, SCADA is the answer to “what is happening?”. In this post we describe a typical architecture, the problems that come up often, and the points to settle before installation. What follows is general engineering practice; every plant and every utility’s specification is different.
Process chain and what to measure
Drinking water: source or well, transmission line, treatment (coagulation, sedimentation, filtration, chlorination), tank, pumping station, distribution network.
Wastewater: sewer, pumping station, screen and grit chamber, biological treatment (aeration basin and blower), final clarification, disinfection, discharge; plus the sludge line.
| Point | Typical measurement / control | Note |
|---|---|---|
| Tank, wet well | Level (ultrasonic or radar), float switch for safety | Keep the float switch as a backup |
| Pumping station | Pump status, pressure, current, constant-pressure or level control with a VFD | Dry-run and blockage alarm |
| Inlet / outlet | Flow (electromagnetic in a full pipe, ultrasonic in an open channel) | Also log the totalizer value |
| Treatment | pH, ORP, turbidity, free chlorine, dissolved oxygen (DO) | Probe maintenance keeps the data reliable |
| Aeration | DO sensor, PID, blower speed (VFD) | DO-based operation instead of fixed speed |
| Dosing | Chlorine, coagulant, polyelectrolyte, pH correction | Flow-proportional dosing is possible |
Architecture: PLC, communications, control center
Each pumping station or treatment unit has a PLC (an RTU or IoT gateway at very small points) and a local HMI. The local HMI lets the operator work on site even when communication is lost. The center holds the SCADA server, the historian and alarm management.
A practical solution for a small operator is usually: a PLC, an HMI, a GSM/4G router and a local or cloud-based SCADA. Large utilities use their own radio network or fiber infrastructure; for example, ASKİ states on its corporate page that its SCADA center communicates with remote stations over its own radio network.
Choosing protocols
- Field: Modbus RTU (flow meters, analyzers and VFDs over RS-485), 4-20 mA, Profinet or EtherNet/IP over the network.
- To the center: Modbus TCP, DNP3 (timestamped event data, common in telemetry), OPC UA, MQTT.
- Which one is mandatory? The protocol or brand requirements of municipalities and water utilities vary by utility; do not decide without checking the tender specification.
Resilience at remote sites
- Event-based (on change) transmission lowers data cost.
- Keep the history locally in the PLC or gateway and synchronize when the connection returns (store-and-forward).
- Define a second channel for critical alarms (email or app notification alongside SMS).
- Use a VPN; do not expose the HMI or VNC port directly to the internet.
The parts of the regulations that concern SCADA
We write the following after checking it against the official texts; for your own plant, consult the current text and the relevant authority.
- The Continuous Wastewater Monitoring Systems Communiqué (Sürekli Atıksu İzleme Sistemleri Tebliği) (Official Gazette 22.03.2015, no. 29303): covers facilities with an installed capacity of 5,000 m³/day and above. SAİS measures the effluent at the point immediately before it mixes into the receiving environment and transfers the data in real time to the Ministry’s central system. The performance test is carried out according to the procedure in TS EN ISO 15839.
- Waters intended for human consumption: If chlorine is used, the free chlorine level at the end point of the network is kept at 0.2-0.5 mg/L; measurements are made every day at the water’s location. In emergencies, chlorination up to a maximum of 1.0 mg/L at the end point is permitted. This shows why end-point measurement is worth tracking as a trend in SCADA.
For the device and software details of SAİS data transmission (measurement interval, mandatory parameters, validity conditions), you need to refer to the full text of the communiqué and the Ministry’s current announcements; we do not give these details here as figures.
Common problems at small operations
| Problem | Likely result | Countermeasure |
|---|---|---|
| Fouled probe, forgotten calibration | “There is data but it cannot be trusted” | Calibration schedule, a maintenance date field in SCADA |
| No GSM signal, alarm does not arrive | Learning about a fault late | Antenna and location, a second alarm channel, connection supervision (heartbeat) |
| Failure to recover after a power outage | Pumps starting all at once, wrong sequence | Restart delays, adequate UPS |
| Dry running, blockage | Pump damage, flooding | Current and level alarms, float switch backup |
| Blower at fixed speed | Unnecessary energy consumption | DO-based VFD control |
| Lightning and overvoltage | Card and modem damage in open terrain | Surge arrester, proper grounding |
| Undocumented software with no backup | Dependence on one person | Program backup, documentation |
| HMI exposed to the internet | Risk of unauthorized access | VPN, strong password, firewall |
Pre-installation checklist
- The points in scope are listed (well, pumping, tank, treatment) and the communication path is determined for each
- Whether you fall under the regulations (e.g. SAİS) and the relevant utility’s specification have been checked
- The output types of the field devices (4-20 mA, Modbus RTU) have been listed
- Every point has a local HMI and local control that keeps working even if communication is lost
- The alarm list, its priorities and who receives each alarm are written down; a second channel is defined
- The pump restart sequence after a power outage and the UPS capacity have been calculated
- Sensor calibration and maintenance intervals are set
- Surge arresters and grounding are planned
- VPN and password policy are defined, no port is left open to the internet
- A backup and documentation of the PLC and SCADA software are written into the delivery terms
Where to start
Do not try to build everything at once. Start with the most critical point, usually the pumping station or tank where there is a risk of flooding or running dry; settle alarms and communication there, then replicate the other points with the same template. Time and cost depend on the number of points, the existing devices and the communication infrastructure, and are determined per project.
If you would like to plan SCADA and remote monitoring for your water or wastewater plant together, take a look at our SCADA installation page.